What is a scope change control system? A. A formal process to review and then decline changes
Question:
What is a scope change control system?
A. A formal process to review and then decline changes to a project B. A formal process to decline a project without management interaction C. A formal process to manage, review, approve, or decline changes to a project D. A formal process to decline all changes to a project without additional funds committed to the project