Q5.8. When the business analyst is preparing a requirements package to send out to potential vendors and
Question:
Q5.8. When the business analyst is preparing a requirements package to send out to potential vendors and when the organization is open to new ideas, then it would be best to issue an:
(a) RFP
(a) RFQ
(c) RFI
(d) RFS