Q5.7. During the later portion of the requirements elicitation stage of the order entry upgrade project, disagreement about requirements causes conflict between the purchasing and receiving departments. What would be an appropriate action by the business analyst?
(a) Since purchasing has the most at stake on this project, their voice is more important.
(b) Escalate to the sponsor.
(c) This is normal and will get solved during the design phase.
(d) This should be handled by the project manager, not the business analyst.