Refer to Table 5-4 and Figure 5-14. Recalculate the variance for each activity on the assumption that
Question:
Refer to Table 5-4 and Figure 5-14. Recalculate the variance for each activity on the assumption that the optimistic and pessimistic estimates were made with a LO6 90 percent probability. Again, recalculate the likelihood that the critical path will be finished in 50 days.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management In Practice
ISBN: 9780470121641
3rd Edition
Authors: Samuel J. Mantel Jr., Jack R. Meredith, Scott M. Shafer, Margaret M. Sutton
Question Posted: