Refer to Table 5-4 and Figure 5-14. Recalculate the variance for each activity on the assumption that
Question:
Refer to Table 5-4 and Figure 5-14. Recalculate the variance for each activity on the assumption that the LO6 optimistic and pessimistic estimates were made with a 95 percent probability. Recalculate the probability that the critical path will be completed in 50 days.