Refer to the network in Figure 5-14. What is the probability that path a-b-c-f will interfere with
Question:
Refer to the network in Figure 5-14. What is the probability that path a-b-c-f will interfere with the promised project completion of 50 days? Recall that the critical path, a-b-d-g-h, had a probability of .86 LO6 for a 50-day completion. What is the probability that both paths will be complete in 50 days?