Refer to the activity network table shown in Exercise 12.1. Suppose that we modified the original table

Question:

Refer to the activity network table shown in Exercise 12.1. Suppose that we modified the original table slightly to show the following predecessor relationships between tasks and resources assigned to perform these activities. Enter this information using MS Project in order to produce a Gantt chart. Assume that each resource has been assigned to the project activity on a full-time basis.

image text in transcribed
a. Using the Resource Usage view, can you determine any warning signs that some member of the project team has been overassigned?
b. Click on the Task Usage view to determine the specific days when there is a conflict in the resource assignment schedule.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: