Suppose in Figure 7-34 everything is the same except Activity Y can start 4 days after Activity
Question:
Suppose in Figure 7-34 everything is the same except Activity Y can start 4 days after Activity V starts, but cannot be finished until 6 days after Activity V is finished.
Show how this changes the values for ES, EF, LS, and LF.