The ___________ must be the basis for a project cost estimate if you plan to create a

Question:

The ___________ must be the basis for a project cost estimate if you plan to create a cost baseline and use earned value management as part of monitoring and controlling costs.

A. project schedule B. cost model C. Gantt chart D. WBS