Use the information on the networks in Figure 11-19 to determine ES, LS, EF, and LF for
Question:
Use the information on the networks in Figure 11-19 to determine ES, LS, EF, and LF for all activities using time buffers (numbers on activities indicate duration in days). For Part
(a) use a 3-week time buffer for the critical path, a 1-week time buffer for every other path that connects to the critical path, and a project target completion time of 29 weeks. For Part
(b) use a 4-week time buffer on the critical path, a 2-week time buffer for every path that connects to the critical path, and a target completion of 45 weeks.