Using the data from Problem 7, calculate the following values: Schedule Variances Planned Value (PV) Earned Value

Question:

Using the data from Problem 7, calculate the following values:
Schedule Variances
Planned Value (PV)
Earned Value (EV)
Schedule Performance Index (SPI)
Estimated Time to Completion
Cost Variances
Actual Cost of Work Performed (AC)
Earned Value (EV)
Cost Performance Index (CPI)
Estimated Cost to Completion
In problem 7
Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through the end of June. Complete the earned value column on the right. Assume the project is planned for a 12-month duration and $250,000 budget.

image text in transcribed
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: