Using the information from the following table, create an AON network activity diagram. a. Calculate each activity
Question:
Using the information from the following table, create an AON network activity diagram.
a. Calculate each activity TE (rounding to the nearest integer); the total duration of the project; its early start, early finish, late start and late finish times; and slack for each activity. Finally, show the project’s critical path.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 978-0133798074
4th edition
Authors: Jeffrey K. Pinto
Question Posted: