Which knowledge areas include processes related to monitoring and controlling? A. project scope, schedule, cost, and quality
Question:
Which knowledge areas include processes related to monitoring and controlling?
A. project scope, schedule, cost, and quality management B. project integration, scope, schedule, cost, and quality management C. project human resource, communications, risk, and procurement management D. all ten knowledge areas