Which of the following is not advice for closing projects or phases? A. You dont need to

Question:

Which of the following is not advice for closing projects or phases?

A. You don’t need to celebrate completing a project, especially if it did not go well.

B. You should capture lessons learned as soon as possible, not just at the end of a project

C. You should include tasks in the WBS for project closing

D. You should assign resources to specific project closing tasks