Which of the following processes involves determining the policies, procedures, and documentation that will be used for

Question:

Which of the following processes involves determining the policies, procedures, and documentation that will be used for planning, executing, and controlling the project schedule?

a. planning schedule management

b. defining activities

c. estimating activity resources

d. activity sequencing