Why should a project manager avoid assigning specific dates to tasks when at all possible during the
Question:
Why should a project manager avoid assigning specific dates to tasks when at all possible during the creation of the network diagram?
A. Dates cannot change; tasks can.
B. Dates require the activity to happen at a specific time.
C. Tasks assigned to dates do not consider successor tasks.
D. Tasks assigned to dates do not consider both successor and predecessor tasks.