Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of
Question:
Activity Average Time
New product development ......... 30 hours
Materials handling ............. 3
Order setup ............... 6
Machine maintenance ........... 3
Order scheduling .............. 1
Inspection of completed order ........ 5
Pack and move to storage or ship ...... 2
Manufacturing assembly .......... 23
Order taking and checking ........ 3
Receiving and stocking raw materials ..... 6
Inspection of raw materials ......... 2
Required
Determine the manufacturing cycle efficiency (MCE) for the recent month. What can you infer from the MCE you calculated?