You are managing an internal project. The initial product test results are very poor and do not

Question:

You are managing an internal project. The initial product test results are very poor and do not meet the minimum customer requirements. If these results are made available to your customer you are afraid that they might cancel the project and this could reflect poorly upon you. Rerunning the product test can be done quickly and inexpensively. Based on this set of circumstances you should A. Be the first to recommend canceling the project B. Inform your external sponsor about the results and wait for a response C. Inform your management immediately and recommend retesting for verification D. Withhold the information from management until you perform additional tests to verify the initial results