You are the project manager for your organization and are working with your project team to create
Question:
You are the project manager for your organization and are working with your project team to create the project scope statement. Part of the scope statement is to define the constraints and assumptions that you must work with in the project. Which one of the following is an example of a project assumption?
A. A predefined schedule B. A predefined budget C. Interoperability of the software and existing hardware D. A requirement to include scalability in the hardware you add to operations