Your company is planning to launch an important new project that starts on January 1 and lasts
Question:
Your company is planning to launch an important new project that starts on January 1 and lasts one year. You estimate that you will need one full-time project manager, two full-time business analysts for the first six months, two full-time senior programmers for the whole year, four full-time junior programmers for the months of July, August, and September, and one full-time technical writer for the last three months. Use the resource_histogram template file from the companion Web site to create a stacked column chart showing a resource histogram for this project, similar to the example in Figure 9-6. Be sure to include a legend to label the types of resources needed. Use appropriate titles and axis labels.
LO.1
Step by Step Answer:
Information Technology Project Management Revised
ISBN: 978-1285847092
7th Edition
Authors: Kathy Schwalbe