Your company is planning to launch an important project starting January 1, which will last one year.
Question:
Your company is planning to launch an important project starting January 1, which will last one year. You estimate that you will need one half-time project manager; two full-time business analysts for the first six months; two full-time marketing analysts for the whole year; four full-time business interns for the months of June, July, and August; and one full-time salesperson for the last three months. Use spreadsheet software such as Microsoft Excel to create a stackedcolumn chart showing a resource histogram for this project, similar to the one shown in Figure 6-8. Be sure to include a legend to label the types of resources needed, and use appropriate titles and axis labels. You can use the resource histogram template on the companion website to make this exercise easier.
Step by Step Answer:
An Introduction To Project Management With A Brief Guide To Microsoft Project 2016
ISBN: 9781544701899
6th Edition
Authors: Kathy Schwalbe