Question: Your company is planning to launch an important new project starting January 1, which will last one year. You estimate that you will need one
Your company is planning to launch an important new project starting January 1, which will last one year. You estimate that you will need one full-time project manager, two full-time business analysts for the first six months, two full-time senior programmers for the whole year, four full-time junior programmers for the months of July, August, and September, and one full-time technical writer for the last three months. Use the resource-histogram template file from the companion Web site to create a stacked column chart showing a resource histogram for this project, similar to the one shown in Figure. Be sure to include a legend to label the types of resources needed. Use appropriate titles and axis labels.
Step by Step Solution
3.28 Rating (157 Votes )
There are 3 Steps involved in it
Number of People 75 320 8 6 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
149-B-M-L-P-M (1252).docx
120 KBs Word File