Your company is planning to launch an important new project starting January 1, which will last one

Question:

Your company is planning to launch an important new project starting January 1, which will last one year. You estimate that you will need one full-time project manager, two full-time business analysts for the first six months, two full-time senior programmers for the whole year, four full-time junior programmers for the months of July, August, and September, and one full-time technical writer for the last three months. Use the resource-histogram template file from the companion Web site to create a stacked column chart showing a resource histogram for this project, similar to the one shown in Figure. Be sure to include a legend to label the types of resources needed. Use appropriate titles and axis labels.