Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have
Question:
Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
b. Identify all paths through the network. Which is the critical path?
c. Which activities have slack time?
d. Identify all burst activities and merge activities.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 978-0133798074
4th edition
Authors: Jeffrey K. Pinto
Question Posted: