Question: Kurt is leading an engineering project. He meets with the stakeholders to define and document all the needs for the engineering project. What activity is

Kurt is leading an engineering project. He meets with the stakeholders to define and document all the needs for the engineering project. What activity is Kurt doing?

A. * Collecting Requirements B. Controlling the Scope C. Creating the WBS D. Verifying the Scope