Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Q. The purpose of this assignment is to explain a final project management plan and retrospective based upon the IT project management activities students have

Q. The purpose of this assignment is to explain a final project management plan and retrospective based upon the IT project management activities students have been developing throughout the course. Using the feedback you received from your peers and instructor on the assignments in Topics 3 to 7, make revisions and finalize your project management plan. The final, revised versions of all plan components created in the Topics 3-7 should be included. In addition, include a five hundred word project retrospective that addresses the following: Discuss what you learned from completion of the group and individual IT project management activities. Evaluate the effectiveness of the project management strategies you employed by discussing what you think worked well in the project plan and what you would do differently if you were assigned a similar project. Provide specific examples related to process, tools, and team dynamics to illustrate your ideas. Submit the final project management plan and retrospective to the instructor. Provide at least five sources and include five intext citations.

Note: Previous three to seven topics assignments are here under for reference.

topic 3:

Work Breakdown Structure (WBS) Draft for a New App Development1.Project Initiation PhaseoDefine Project Objectives and GoalsConduct stakeholder interviews to gather input on app objectives.Identify project constraints and establish clear goals for success.oConduct Stakeholder AnalysisIdentify key stakeholders and their roles in app development.Assess stakeholder expectations, concerns, and levels of influence.oDevelop Project CharterDefine the app scope, objectives, and boundaries.Establish project authority, responsibilities, and governance structure.2.Planning PhaseoGather Project RequirementsConduct user interviews, surveys, and workshops to elicit app requirements.Document functional and non-functional requirements in detail.oCreate Project Scope StatementDefine the app's deliverables, objectives, and exclusions.Establish acceptance criteria for app deliverables.oDevelop WBS DictionaryDefine a hierarchical breakdown of app features, functionalities, and deliverables.Document detailed descriptions and specifications for each WBS element.3.Execution PhaseoProcure Necessary ResourcesIdentify resource requirements (e.g., developers, designers, servers).Develop a procurement plan and acquire necessary resources.oConduct Team TrainingIdentify training needs based on app requirements and team skill gaps.Arrange training sessions or workshops to enhance team capabilities.oBegin Development ActivitiesExecute app development tasks according to the established project plan and schedule.Monitor progress and address any deviations or roadblocks promptly.4.Monitoring and Controlling PhaseoTrack Project ProgressMonitor task completion status and milestone achievements.Compare actual progress against planned milestones and deliverables.oManage Changes to ScopeDocument and assess change requests to scope, schedule, or budget.Obtain approval for scope changes and update project documentation.oPerform Quality AssuranceConduct regular quality reviews and audits to ensure app quality and functionality.Implement corrective actions to address any deviations from quality requirements.5.Closing PhaseoComplete Project DeliverablesFinalize all app development tasks and activities to deliver agreed-upon outcomes.Obtain sign-off from stakeholders on the completion of app deliverables.oObtain Client AcceptanceEnsure that the app meets client expectations and requirements.Obtain formal acceptance and approval from the client for app launch.oConduct Project Review and Lessons LearnedEvaluate app performance against initial objectives and goals.Identify successes, challenges, and areas for improvement through lessons learned documentation.Scope Management Plan:Scope Statement: Clearly define app objectives, functionalities, and boundaries.Scope Verification: Ensure that all app deliverables meet agreed-upon specifications.Scope Change Control: Establish a process for managing changes to app scope, including documentation, approval, and impact analysis.Scope Baseline: Document the approved app scope and ensure that all changes are properly reflected and communicated.Project Schedule:Define app milestones, tasks, and dependencies.Develop a Gantt chart or project timeline to visualize app development activities and durations.Allocate resources and estimate task durations accurately.Regularly update and monitor the app development schedule to ensure timely completion.Budget Management Plan:Cost Estimation: Estimate app development costs based on resource requirements, labor rates, and other expenses.Budget Allocation: Allocate funds to various app development activities and phases.Cost Control: Monitor app development expenses and implement measures to prevent cost overruns.Financial Reporting: Provide regular reports on app development expenditures and budget status to stakeholders.Risk Management Plan:Risk Identification: Identify potential risks associated with app development, such as technical challenges, resource constraints, or changes in market demand.Risk Analysis: Assess the likelihood and impact of each identified risk on the project's objectives and deliverables.Risk Response Planning: Develop strategies to mitigate, avoid, transfer, or accept identified risks.Risk Monitoring and Control: Regularly monitor and review identified risks throughout the app development lifecycle, implementing risk response strategies as necessary.Communication Plan:Stakeholder Communication: Define communication channels and protocols for engaging with stakeholders throughout the app development process.Team Communication: Establish regular team meetings and communication platforms to ensure effective collaboration and information sharing among team members.Reporting Mechanisms: Determine reporting frequency and formats for project progress updates, status reports, and milestone achievements.Issue Escalation Process: Outline procedures for escalating issues and concerns to appropriate stakeholders for resolution.Resource Management Plan:Resource Identification: Identify human resources, tools, and equipment required for app development.Resource Allocation: Assign resources to specific tasks and activities based on skillsets, availability, and project requirements.Resource Tracking: Monitor resource utilization and availability throughout the project lifecycle, making adjustments as necessary to ensure optimal resource allocation.Resource Training and Development: Provide training and professional development opportunities to enhance team capabilities and expertise.Procurement Management Plan:Procurement Planning: Identify external vendors or suppliers needed for app development and define procurement requirements.Vendor Selection: Evaluate potential vendors based on criteria such as expertise, cost, and reliability, and select the most suitable vendors for procurement.Contract Management: Negotiate and finalize contracts with selected vendors, outlining deliverables, timelines, and payment terms.Vendor Performance Monitoring: Monitor vendor performance and adherence to contract terms, addressing any issues or concerns as they arise.Quality Management Plan:Quality Planning: Define quality standards and metrics for app development, ensuring that deliverables meet predetermined criteria.Quality Assurance: Implement processes and procedures to verify that app development activities comply with quality standards and requirements.Quality Control: Conduct regular inspections, reviews, and tests to identify and correct defects or deviations from quality standards.Continuous Improvement: Establish mechanisms for capturing feedback, lessons learned, and opportunities for improvement throughout the app development lifecycle, fostering a culture of continuous improvement.Change Management Plan:Change Identification: Establish protocols for identifying and documenting changes to project scope, requirements, or deliverables.Change Assessment: Evaluate proposed changes in terms of their impact on project objectives, timelines, and resources.Change Approval: Define a formal process for reviewing and approving changes, involving relevant stakeholders as necessary.Change Implementation: Implement approved changes in a timely manner, ensuring that all project documentation is updated accordingly.Integration Management Plan:Integration Strategy: Define the approach for integrating various app development activities, processes, and components to ensure seamless coordination and alignment.Integration Scope: Identify key integration points and dependencies within the app development lifecycle, addressing any potential conflicts or gaps.Integration Implementation: Execute integration activities according to the defined strategy and schedule, monitoring progress and resolving issues as they arise.Integration Testing: Conduct thorough testing and validation of integrated app components to verify functionality, performance, and compatibility.Conclusion:This draft Work Breakdown Structure (WBS) and associated plans provide a comprehensive framework for managing the development of a new app. By breaking down the project into manageable tasks and defining clear processes and procedures for scope, schedule, budget, risk, communication, resource, procurement, quality, change, and integrationmanagement, this plan sets the foundation for successful app development. Continuous monitoring, evaluation, and adaptation throughout the project lifecycle will be essential to ensure that the project stays on track and delivers the desired outcomes

Feedback

Very good details, content, and clarity in your work breakdown structure.

Topic 4

Risk Management Plan Project DraftConstruction of a New Office Building1.Introduction:Providing an overview of the construction project, including its objectives, scope, and stakeholders.Outline the purpose and scope of the risk management plan.2.Risk Identification:Identify potential risks associated with the construction project, including:Safety hazards at the construction site.Weather-related delays.Budget overruns due to unforeseen expenses.Regulatory compliance issues.Supply chain disruptions.Changes in project scope or requirements.3.Risk Analysis:Assess the likelihood and impact of each identified risk on project objectives.Prioritize risks based on their severity and potential consequences for project success.4.Risk Response Planning:Develop strategies to address identified risks:Safety hazards: Implement strict safety protocols, provide adequate training, and conduct regular inspections.Weather-related delays: Develop contingency plans, adjust the project schedule accordingly, and secure insurance coverage.Budget overruns: Monitor expenses closely, negotiate contracts with vendors, and identify potential cost-saving measures.Regulatory compliance issues: Stay informed about relevant regulations, engage legal counsel, and allocate resources for compliance efforts.Supply chain disruptions: Diversify suppliers, maintain buffer inventory, and establish alternative transportation routes.Changes in project scope: Establish change management procedures, assess impact on schedule and budget, and obtain client approval.5.Risk Monitoring and Control:Implement processes for ongoing monitoring of identified risks.Establish trigger points and thresholds for risk escalation and response.Regularly review and update the risk management plan to reflect changes in project dynamics.6.Communication and Reporting:Define communication channels and reporting mechanisms for sharing risk-related information with stakeholders.Ensure timely and transparent communication about risk status, mitigation efforts, and any changes to the risk management plan.7.Documentation and Documentation Management:Maintain a centralized repository for all risk-related documentation, including risk registers, assessments, and mitigation plans.Implement version control and access management protocols to ensure the integrity and confidentiality of risk information.8.Training and Awareness:Provide training and awareness programs to project team members to enhance understanding of risk management principles and processes.Foster a culture of risk awareness and proactive risk management within the project team.9.Continuous Improvement:Conduct regular reviews and updates of the risk management plan to accommodate changes in project dynamics and emerging risks.Incorporate lessons learned from previous projects to refine and enhance risk management practices.This risk management plan for the construction of a new office building provides a structured approach to identifying, assessing, and mitigating risks to ensure project success and stakeholder satisfaction.

Feedback

Roshan

Super fantastic details and content in this assignment.

Thanks

Topic 5

A Quality Management Plan for Husky Air - Pilot AngelsDraftIntroductionThe Quality Management Plan for Husky Air - Pilot Angels aims to ensure that the project meets stakeholder needs and expectations while maintaining high standards of quality throughout its lifecycle. This plan outlines the approach to quality management, human resource management, and communication management for the project.Quality Management Approach:Our approach to quality management focuses on planning, developing, and managing a quality environment conducive to meeting stakeholder expectations. We will prioritize the delivery of high-quality services to our clients while adhering to industry standards and best practices.Quality PlanningQuality planning involves identifying relevant quality standards and metrics for the project. We will establish clear quality requirements and ensure they are documented and communicated effectively to all project stakeholders. This will enable us to monitor and measure project performance against established quality criteria.Quality AssuranceQuality assurance processes will be implemented to ensure that project activities comply with defined quality standards. We will establish procedures for preventing defects and errors during project execution, thereby minimizing rework and ensuring the quality of deliverables.Quality ControlQuality control mechanisms will be put in place to monitor and measure project performance against quality standards. We will regularly assess project outputs and identify any deviations from the established quality criteria. Prompt corrective actions will be taken to address any quality issues that arise during the project.Human Resource ManagementHuman resource management strategies will focus on creating and developing a high-performing project team. We will provide training and support to team members to enhance their skills and competencies. Additionally, we will address the behavioral aspects of project management to ensure effective collaboration and teamwork.Communication ManagementCommunication management will involve timely and accurate dissemination of project information to stakeholders. We will establish clear channels of communication and ensure that relevant project updates are communicated effectively to all stakeholders.Earned Value AnalysisAn earned value analysis will be conducted using Microsoft Project to track project performance and progress. This analysis will provide valuable insights into project cost and schedule performance, allowing us to make informed decisions and take corrective actions as needed.In conclusion, the Quality Management Plan for Husky Air - Pilot Angels outlines our commitment to delivering a high-quality project that meets stakeholder needs and expectations. By implementing robust quality management processes, human resource management strategies, and communication management practices, we aim to ensure the successful completion of the project.Reference:Abbas, J. (2020). Impact of total quality management on corporate green performance through the mediating role of corporate social responsibility. Journal of Cleaner Production, 242, 118458.

Feedback

Very good details, and content in your quality plan.

THanks

Topic 6

Change Management Plan for ERP ImplementationThe Change Management Plan outlined below is tailored specifically for the implementation of a new Enterprise Resource Planning (ERP) system in a large manufacturing company. ERP implementation projects are complex and often involve significant organizational change. This plan aims to ensure smooth transitions, minimal disruption, and maximum stakeholder satisfaction throughout the implementation process.1. Change Management Process:1.1 Change Identification:Establish formal mechanisms for identifying potential changes, such as regular project status meetings and stakeholder consultations specifically focused on ERP implementation challenges.Utilize change request forms to document change proposals related to ERP implementation comprehensively, including description, rationale, impact assessment, and proposed solution.Define criteria for evaluating the significance and urgency of ERP-related change requests, considering factors like project objectives, scope, budget, and schedule.1.2 Change Assessment and Evaluation:Assess the feasibility, potential impacts, and alignment with project objectives of ERP-related change requests upon receiving them.Conduct thorough impact analysis to evaluate the ripple effects of proposed changes on ERP implementation, including impacts on project scope, schedule, resources, and quality.Engage relevant stakeholders, including project sponsors, ERP system users, and process owners, in the evaluation process to ensure holistic consideration.1.3 Change Approval and Prioritization:Establish a dedicated ERP Change Control Board (CCB) comprising key stakeholders from different departments to review and approve ERP-related change requests.Develop predefined criteria for prioritizing ERP-related change requests based on their strategic importance, urgency, and potential impact on ERP project deliverables.Ensure transparent communication of CCB decisions related to ERP changes to all project team members and stakeholders involved in ERP implementation.2. Communication and Stakeholder Engagement:2.1 Communication Plan:Develop a comprehensive communication plan specifically for ERP implementation activities, outlining the channels, frequency, and content of communication.Tailor communication strategies to suit the preferences and information needs of diverse stakeholders involved in ERP implementation, including project sponsors, ERP system users, and affected departments.Implement regular updates, progress reports, and change logs specifically focused on ERP implementation to keep stakeholders informed about the status of ERP-related change requests and their implications on project execution.2.2 Stakeholder Engagement Strategy:Identify key stakeholders involved in ERP implementation, distinguishing between ERP system users, process owners, and executives.Foster stakeholder buy-in and ownership by soliciting their input during ERP-related change identification, evaluation, and implementation stages.Address stakeholder concerns and resistance specific to ERP implementation through proactive communication, change impact assessments, and stakeholder engagement workshops focusing on ERP benefits and training opportunities.3. Training and Transition Management:3.1 Training Needs Analysis:Conduct a thorough analysis of training needs specific to ERP implementation to identify knowledge and skill gaps among end-users and key stakeholders.Develop targeted ERP training programs and materials to equip project team members, ERP system users, and process owners with the competencies required to adapt to the new ERP system effectively.Implement a phased approach to ERP training delivery, aligning training schedules with ERP project milestones and deployment timelines to ensure timely skill acquisition.3.2 Transition Planning:Develop a detailed transition plan outlining the sequence of activities and responsibilities for implementing ERP-related changes.Define clear roles and responsibilities for ERP change implementation, ensuring accountability and coordination among project team members, ERP system users, and process owners.Anticipate potential challenges and risks associated with ERP implementation, and develop mitigation strategies to address them proactively, focusing on data migration, system integration, and user adoption challenges.4. Risk Management and Contingency Planning:4.1 Risk Identification and Assessment:Conduct a comprehensive risk assessment specific to ERP implementation, identifying potential risks such as data loss, system downtime, and user resistance.Utilize risk identification techniques like SWOT analysis and expert judgment to uncover potential threats and opportunities specific to ERP implementation.Evaluate the likelihood and impact of identified risks using qualitative and quantitative risk analysis techniques to prioritize mitigation efforts focused on ERP project success.4.2 Risk Mitigation and Contingency Planning:Develop risk mitigation strategies specific to ERP implementation to proactively address identified risks and minimize their impact on project objectives.Implement risk response strategies such as data backup and recovery plans, stakeholder engagement initiatives, and user training programs tailored to ERP system functionality.Develop contingency plans outlining alternative courses of action and escalation procedures to be activated in the event of unforeseen challenges or disruptions specific to ERP implementation.5. Performance Measurement and Continuous Improvement:5.1 Key Performance Indicators (KPIs):Define measurable KPIs aligned with ERP project objectives to monitor the effectiveness of change management activities specific to ERP implementation.Establish baseline performance metrics to track changes in ERP project scope, schedule, budget, quality, and stakeholder satisfaction throughout the implementation process.Regularly monitor ERP-related KPIs and performance indicators to identify trends, deviations, and areas for improvement, focusing on ERP system usability, data accuracy, and business process efficiency.5.2 Lessons Learned and Best Practices:Facilitate regular lessons learned sessions throughout ERP implementation to document best practices, success stories, and challenges encountered.Document lessons learned specific to ERP implementation to inform future projects and initiatives, focusing on ERP system selection, implementation methodology, and stakeholder engagement strategies.Encourage knowledge sharing and cross-functional collaboration among project teams and departments to leverage collective insights and expertise specific to ERP implementation challenges and opportunities.ConclusionEffective change management is essential for the successful implementation of a new Enterprise Resource Planning (ERP) system in a large manufacturing company. By adhering to the strategies outlined in this Change Management Plan tailored to ERP implementation, project teams can navigate change confidently, minimize disruption, and maximize stakeholder satisfaction. Continuous monitoring, stakeholder engagement, and risk management specific to ERP implementation are key to fostering adaptability and driving continuous improvement in ERP project outcomes and organizational performance.Reference:Marchewka, J. T. (2016). Information technology project management: Providing measurable organizational value (5th ed.). Hoboken, NJ: Wiley. ISBN-13: 9781118911013

Feedback

Roshan

Well-developed ideas, including introduction of new ideas, stimulates discussion. No mechanical issues.

Thanks

Topic 7.

1Rough Draft - Project Implementation and Closure PlanRoshan DahalMGT-665: IT Project ManagementGrand Canyon UniversityDr. Brodie Johnson04/23/20242Introduction:Navigating a project's journey from start to finish demands careful planning and execution. The project implementation and closure plan provide essential guides for steering through these phases, ensuring smooth project delivery and closure. These plans outline crucial activities and strategies, promoting effective project management and fostering ongoing improvement within the organization.Project Implementation Plan1.Introduction:Provide an overview of the project's goals, objectives, and scope.Outline the importance of effective implementation for achieving project success.2.Project Scope:Define the project scope, including deliverables, milestones, and timeline.Clarify roles and responsibilities for team members involved in the implementation process.3.Project Resources:Identify and allocate necessary resources, such as personnel, equipment, and budget.Ensure availability of required tools and technologies for smooth implementation.4.Project Activities:Break down the project into actionable tasks and activities.3Establish dependencies and sequence of activities to ensure efficient execution.5.Risk Management:Identify potential risks and develop mitigation strategies.Monitor risks throughout the implementation phase and adjust plans as needed.6.Communication Plan:Define communication channels and frequency for project updates.Ensure clear and consistent communication among team members and stakeholders.7.Quality Assurance:Establish quality standards and metrics to measure project success.Conduct regular reviews and inspections to ensure compliance with standards.8.Monitoring and Control:Implement monitoring mechanisms to track progress against objectives.Establish control processes to address deviations and ensure project alignment with goals.Project Closure Plan1.Closure Criteria:Define criteria for project closure, such as completion of deliverables and achievement of objectives.Ensure alignment with stakeholder expectations and project requirements.2.Transition Plan:Develop a plan for transitioning project outcomes to stakeholders or end-users.Provide training and support to facilitate smooth adoption of project deliverables.43.Documentation:Compile project documentation, including reports, lessons learned, and final deliverables.Ensure documentation is organized and accessible for future reference.4.Celebration and Recognition:Acknowledge the efforts of team members and stakeholders in achieving project goals.Celebrate milestones and successes to foster a positive project closure experience.5.Feedback Collection:Solicit feedback from team members, stakeholders, and end-users to identify areas for improvement.Use feedback to inform future projects and enhance organizational processes.6.Contractual Closure:Close out any contractual obligations and ensure compliance with legal requirements.Obtain formal acceptance of project deliverables from stakeholders.7.Lessons Learned:Conduct a comprehensive review of the project to identify successes, challenges, and lessons learned.Document key insights and recommendations for future projects.The project implementation and closure plan outlined above provides a structured approach to managing the project lifecycle from initiation to closure. By addressing key aspects5such as scope, resources, activities, risk management, communication, quality assurance, and monitoring, the implementation plan ensures that the project progresses efficiently towards its objectives. Additionally, the closure plan defines clear criteria for project completion, outlines transition procedures, addresses documentation and contractual requirements, and emphasizes the importance of celebrating achievements and collecting feedback. By adhering to these plans, project teams can navigate challenges effectively, maintain stakeholder engagement, and deliver successful outcomes. Moreover, the focus on continuous improvement through lessons learned and feedback collection ensures that valuable insights are captured for future projects, contributing to organizational growth and development. Overall, the project implementation and closure plan serve as essential guides for achieving project success and promoting a culture of excellence in project management.

Feedback

Roshan;

Clear evidence of critical thinking - application, analysis, synthesis, and evaluation of topic content.

Thanks

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Marketing Management

Authors: David C Bojanic, Robert D Reid

6th Edition

1119195152, 9781119195153

More Books

Students also viewed these General Management questions

Question

1. To gain knowledge about the way information is stored in memory.

Answered: 1 week ago