You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of an

Question:

You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of an organization’s operating system on 236 servers. You performed this project under contract. You are in the Close Procurements process and know that you should document which of the following? (Choose the best response.)

A. Administrative closure procedures B. Close Procurements procedures C. Formal acceptance D. Product verification