You expect future project performance to be consistent with the project performance experienced to date. If BAC

Question:

You expect future project performance to be consistent with the project performance experienced to date. If BAC = 800, ETC = 275, PV = 300, cumulative AC = 200, EV = 250, and cumulative CPI = 1.25, what is the EAC?

A. 640 B. 750 C. 600 D. 550