=11-19 Tom Schriber, a director of personnel of Management Resources, Inc., is in the process of designing

Question:

=11-19 Tom Schriber, a director of personnel of Management Resources, Inc., is in the process of designing a program that its customers can use in the job-finding process. Some of the activities include preparing resumés, writing letters, making appointments to see prospective employers, researching companies and industries, and so on. Some of the information on the activities is shown in the following table:

Activity Days Immediate a m b Predecessors A 8 10 12 —

B 6 7 9 —

C 3 3 4 —

D 10 20 30 A E 6 7 8 C F 9 10 11 B, D, E G 6 7 10 B, D, E H 14 15 16 F I 10 11 13 F J 6 7 8 G, H K 4 7 8 I, J L 1 2 4 G, H

(a) Construct a network for this problem.

(b) Determine the expected time and variance for each activity.

(c) Determine ES, EF, LS, LF, and slack for each activity.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis For Management

ISBN: 9789332578692

12th Edition

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

Question Posted: