=11-34 The Laurenster Corporation has determined the client will pay them a $10,000 bonus if they complete

Question:

=11-34 The Laurenster Corporation has determined the client will pay them a $10,000 bonus if they complete the project in Problem 11-33 in 14 weeks or less.

The associated normal times and costs as well as the crash times and costs are shown below.

Activity Normal Time Crash Time Normal Cost ($)

Crash Cost

($)

A 3 2 600 1,200 B 6 4 1,200 2,400 C 5 2 1,200 2,400 D 4 3 1,200 1,800 Activity Normal Time Crash Time Normal Cost ($)

Crash Cost

($)

E 7 6 1,200 1,800 F 7 4 1,200 3,000 G 5 1 2,400 4,800 H 5 2 1,200 3,000 I 5 3 1,800 2,400 J 2 2 300 300 K 4 4 300 300 L 3 3 300 300 Considering the costs involved to crash the project, determine if the Laurenster Corporation should crash the project to 14 weeks to receive the bonus.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis For Management

ISBN: 9789332578692

12th Edition

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

Question Posted: