=7. In PERT, slack time equals a. EF + t. b. LS - ES. c. 0. d.

Question:

=7. In PERT, slack time equals

a. EF + t.

b. LS - ES.

c. 0.

d. EF - ES.

e. none of the above.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis For Management

ISBN: 9789332578692

12th Edition

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

Question Posted: