= (b) Formulate an LP problem to crash this project to 10 weeks. Activity Normal Time Crash
Question:
=
(b) Formulate an LP problem to crash this project to 10 weeks.
Activity Normal Time Crash Time Normal Cost
($)
Crash Cost
($)
Immediate Predecessors A 3 2 1,000 1,600 —
B 2 1 2,000 2,700 —
C 1 1 300 300 —
D 7 3 1,300 1,600 A E 6 3 850 1,000 B F 2 1 4,000 5,000 C G 4 2 1,500 2,000 D, E
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Quantitative Analysis For Management
ISBN: 9789332578692
12th Edition
Authors: Barry Render, Ralph M. Stair, Michael E. Hanna
Question Posted: