= (b) List all the paths in this network. After the crashing in part (a) has been
Question:
=
(b) List all the paths in this network. After the crashing in part
(a) has been done, what is the time required for each path? If the project completion time must be reduced another week so that the total time is 15 weeks, which activity or activities should be crashed? Solve this by inspection. Note that it is sometimes better to crash an activity that is not the least cost for crashing if it is on several paths rather than to crash several activities on separate paths when there is more than one critical path.