The earliest start time for an activity is equal to a. the largest EF of the immediate
Question:
The earliest start time for an activity is equal to
a. the largest EF of the immediate predecessors.
b. the smallest EF of the immediate predecessors.
c. the largest ES of the immediate predecessors.
d. the smallest ES of the immediate predecessors.