Which of the following statements about PERT are true? a. It assumes that we do not know
Question:
Which of the following statements about PERT are true?
a. It assumes that we do not know ahead of time what activities must be completed.
b. It assumes that activity time estimates follow the normal probability distribution.
c. It is a network technique that uses three time estimates for each activity in a project.
d. It is a deterministic network technique that allows for project crashing.