When PERT is used and probabilities are found, one of the assumptions that is made is that

Question:

When PERT is used and probabilities are found, one of the assumptions that is made is that

a. all activities are on the critical path.

b. activity times are independent.

c. all activities have the same variance.

d. the project variance is equal to the sum of the variances of all activities in the project.

e. all of the above.