The latest finish time for an activity is found during the backward pass through the network. The

Question:

The latest finish time for an activity is found during the backward pass through the network. The latest finish time is equal to

a. the largest LF of the activities for which it is an immediate predecessor.

b. the smallest LF of the activities for which it is an immediate predecessor.

c. the largest LS of the activities for which it is an immediate predecessor.

d. the smallest LS of the activities for which it is an immediate predecessor.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis For Management

ISBN: 213168

12th Edition

Authors: Barry Render ,Ralph M. Stair ,Michael E. Hanna

Question Posted: