Which of the following is the latest finish time (LF)? a. the latest time an activity can

Question:

Which of the following is the latest finish time (LF)?

a. the latest time an activity can end without delaying the entire project

b. the latest time an activity can begin without delaying the entire project

c. the earliest time an activity can begin without violation of immediate predecessor requirements

d. b and c