1. The second ring in the network of relationships for project managers includes all of the following except: a) Other project managers b) Customers c)
1. The second ring in the network of relationships for project managers includes all of the following except:
a) Other project managers
b) Customers
c) Functional managers
d) Top management
e) Project sponsors
2. In a survey of project managers, approximately what percentage reported that they encountered ethical issues in their work?
a) 22 percent
b) 40 percent
c) 65 percent
d) 81 percent
e) 100 percent
3. Which of the following requires more management rather than leadership?
a) Taking corrective action
b) Changes in project scope
c) Technological stalemates
d) Breakdowns in coordination between people
e) All of these require the same level of management
4. During which stage of team development is high performance not a top priority and team member emotions run from upbeat to depressed?
a) Norming
b) Storming
c) Performing
d) Adjourning
e) Forming
5. One problem new project managers experience is that it takes time to establish a sense of character and competency.
a) True
b) False
Step by Step Solution
3.32 Rating (161 Votes )
There are 3 Steps involved in it
Step: 1
1 b Customers 2 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started