Question
1. In which of the following theories does the project group transition from a lower level to a higher level of performance about halfway through
1. In which of the following theories does the project group transition from a lower level to a higher level of performance about halfway through the project?
a) Nominal Group Technique
b) Five Stage Team Development Model
c) Punctuated Equilibrium Model of Group Development
d) Dysfunctional Transition Model
e) Synergistic Transition Development Model
2. Which of the following is not one of the most significant sources of conflict during the project planning phase?
a) Priorities
b) Procedures
c) Schedule
d) Technical requirements
e) Costs
3. The first step in facilitating group decision making is to:
a) Call a meeting to discuss the problem
b) Identify the problem
c) Agree that there is a problem
d) Quantify the problem
e) Generate alternatives
4. Good time management for project managers includes initiating contact with key stakeholders only when there is a valid issue to deal with.
a) True
b) False
5. All of the following have been found to be good for running effective project meetings except:
a) Start meetings on time regardless of whether everyone is present
b) Identify an adjournment time
c) Thoroughly document all decisions
d) Prepare and distribute an agenda prior to the meeting
e) All of these are good for effective meetings
Step by Step Solution
3.48 Rating (151 Votes )
There are 3 Steps involved in it
Step: 1
1 c Punctuated Equilibrium Mo...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started