a) Use the following information to construct a network diagram using AON notation. Activity Activity time (weeks) Immediate Predecessors(s) A 3 None B 4 A

a) Use the following information to construct a network diagram using AON notation.



Activity

Activity time

(weeks)

Immediate

Predecessors(s)

A

3

None

B

4

A

C

2

B

D

5

B

E

4

C

F

3

D

G

2

E,F


Using the network diagram from problem 1:

b) Calculate the project completion time.

c) Determine which activities are on the critical path.

Step by Step Solution

3.34 Rating (148 Votes )

There are 3 Steps involved in it

Step: 1

a The following nomenclature has been used Late start Activity name Late finish Ear... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Document Format ( 2 attachments)

PDF file Icon
6091559050dc1_22292.pdf

180 KBs PDF File

Word file Icon
6091559050dc1_22292.docx

120 KBs Word File

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: R. Dan Reid, Nada R. Sanders

4th edition

9780470556702, 470325046, 470556706, 978-0470325049

More Books

Students also viewed these General Management questions