Question: Use the following information to construct a network diagram using AON notation. Using the network diagram from problem 1: a. Calculate the project completion time
Use the following information to construct a network diagram using AON notation.

Using the network diagram from problem 1:
a. Calculate the project completion time
Path _______________Path Duration
b. Determine which activities are on the critical path.
Activity ABCDEFG Activity Time (weeks) NWAUNAW 4 2 5 2 Immediate Predecessor(s) none ARBUAH D
Step by Step Solution
3.29 Rating (152 Votes )
There are 3 Steps involved in it
To solve the problem well construct the network diagram using the AON Activity on Node notation calc... View full answer