Question
Use the following project information: Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 6 11
Activity | Optimistic Time Estimate (weeks) | Most Likely Time Estimates (weeks) | Pessimistic Time Estimates (weeks) | Immediate Predecessor(s) |
A | 2 | 6 | 11 | none |
B | 3 | 5 | 9 | A |
C | 3 | 8 | 13 | A |
D | 5 | 6 | 10 | B |
E | 6 | 9 | 17 | C |
F | 4 | 4 | 5 | D, E |
G | 2 | 5 | 10 | D, E |
H | 4 | 6 | 11 | F |
I | 4 | 8 | 11 | G |
J | 3 | 3 | 3 | H, I |
A.)Using the information given, construct a network diagram using AON notation.
B.) Using the information given, calculate the expected time for each of the project activities.
C.) Using the information given, calculate the variance for each of the project activities.
D.) Using your results from Problems B and C, Calculate the completion time for this project.
E.) Identify the activities included on the critical path of this project.
F.) Using your results from Problem D and E, Calculate the probability that the project will be completed in 38 weeks.
G.) Calculate the probability that the project will be completed in 42 weeks.
Step by Step Solution
3.31 Rating (163 Votes )
There are 3 Steps involved in it
Step: 1
AUsing the information given construct a network diagr am using AON notation B Using the information given calculate the expected time for each of the ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started