Question

1 Approved Answer

Activity D on a CPM network has predecessors B and C. and has successor F. D has duration 6. Bs earliest finish is 18. While

Activity D on a CPM network has predecessors B and C. and has successor F. D has duration 6. B’s earliest finish is 18. While C’s is 20. F’s late start is 26. Which of the following is definitely true

A. D is critical and has zero slack

B. B is a critical activity.

C. F is critical, and has zero slack.

D. D has no slack but is not critical.

E. C is completed before B.

Step by Step Solution

3.49 Rating (159 Votes )

There are 3 Steps involved in it

Step: 1

A D is ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Document Format ( 2 attachments)

PDF file Icon
60953e92bf47e_25675.pdf

180 KBs PDF File

Word file Icon
60953e92bf47e_25675.docx

120 KBs Word File

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing and Assurance Services

Authors: Timothy Louwers, Robert Ramsay, David Sinason, Jerry Straws

6th edition

978-1259197109, 77632281, 77862341, 1259197107, 9780077632281, 978-0077862343

More Books

Students also viewed these Mathematics questions