Question: Activity D on a CPM network has predecessors B and C. and has successor F. D has duration 6. Bs earliest finish is 18. While
Activity D on a CPM network has predecessors B and C. and has successor F. D has duration 6. B’s earliest finish is 18. While C’s is 20. F’s late start is 26. Which of the following is definitely true
A. D is critical and has zero slack
B. B is a critical activity.
C. F is critical, and has zero slack.
D. D has no slack but is not critical.
E. C is completed before B.
Step by Step Solution
3.49 Rating (159 Votes )
There are 3 Steps involved in it
We need to analyze the given information about the activities in the CPM Critical Path Method networ... View full answer