Old City Photographics (OCP) specializes in processing traditional 35 mm film negatives. OCP offers three packages to its customers. With the standard package, the customer
Old City Photographics (OCP) specializes in processing traditional 35 mm film negatives. OCP offers three packages to its customers. With the standard package, the customer gets a set of 6”x4” prints. The deluxe package adds to the standard package a CD-ROM of high resolution scans of the pictures. Finally, the pro package is similar to the deluxe package in that it comes with a CD-ROM, except that the customer gets a contact print rather than a set of prints. On average, OCP receives 15 jobs per hour consisting of 50 percent standard, 30 percent deluxe, and 20 percent pro.
All jobs require 2 min per unit to process the film at the processing station. Making the 6”x4” prints takes 4 min per unit at the print station. Scanning the film on to a CD-ROM takes 5 min per unit at the scanning station. Making the contact print takes 10 min per unit at the contact print station.
Required:
A. How many jobs will arrive per hour at each station?
B. Determine the bottleneck and flow rate.
Step by Step Solution
3.49 Rating (152 Votes )
There are 3 Steps involved in it
Step: 1
A Hourly arrival rate of jobs at station for standard print 50 percent of 15 75 Hourly arrival rate ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
609340c5eef7c_23590.pdf
180 KBs PDF File
609340c5eef7c_23590.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started