The equations for the acceptance and rejection lines for an item-by-item sequential sampling plan are given as follows:

X A = -0.95 + 0.06 n

X R = 3.22 + 0.06 n

(A) An inspector tests 18 item without finding a single defective one. Under this plan should he have decided to accept the lot before reaching the 18 th item? Explain.

(B) What is the minimum number of items he should inspect before rejecting a lot?

Step by Step Solution

3.49 Rating (156 Votes )

There are 3 Steps involved in it

Step: 1

X A 095 006 n X R 322 006 n A n 1 18 X A 0 095 006n 0 006n 095 n 0... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Document Format ( 2 attachments)

PDF file Icon
6091797ebe10f_22386.pdf

180 KBs PDF File

Word file Icon
6091797ebe10f_22386.docx

120 KBs Word File

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Controlling and Improving Quality

Authors: Douglas C. Montgomery, Cheryl L. Jennings, Michele E. Pfund

1st edition

471697915, 978-0471697916

More Books

Students also viewed these Accounting questions

Question

What other requirements do they have for admission?

Answered: 1 week ago

Question

Given the following information, prepare a statement of cash flows

Answered: 1 week ago