Question

1 Approved Answer

The following project is at the end of its 6 th week. Find the cost and schedule variances. Also find the CPI and SPI. Then

The following project is at the end of its 6 th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project.

Activity b d e Predecessor Duration (wks) a a b.c wwww 2 3 2 5 4 Budget ($) 300 200 250 600 400 Actual Cost ($) 400 180 300 400 200 % Complete 100 100 100 20 20

Step by Step Solution

3.57 Rating (154 Votes )

There are 3 Steps involved in it

Step: 1

Draw the Network Diagram Network Diagram Determine the Critical Path After drawing the ne... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions

Question

How is this person feeling about the situation?

Answered: 1 week ago