The following project is at the end of its 6 th week. Find the cost and schedule variances. Also find the CPI and SPI. Then
The following project is at the end of its 6 th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project.
Activity b d e Predecessor Duration (wks) a a b.c wwww 2 3 2 5 4 Budget ($) 300 200 250 600 400 Actual Cost ($) 400 180 300 400 200 % Complete 100 100 100 20 20
Step by Step Solution
3.57 Rating (154 Votes )
There are 3 Steps involved in it
Step: 1
Draw the Network Diagram Network Diagram Determine the Critical Path After drawing the ne...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Project Management in Practice
Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco
4th edition
470533013, 978-0470533017
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App