The gain from a project is equally likely to have any value between -$0.15 million and +$0.85 million. What is the 99% value at risk?
The gain from a project is equally likely to have any value between -$0.15 million and +$0.85 million. What is the 99% value at risk?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Expected gain 05 015 05 085 ...Get Instant Access to Expert-Tailored Solutions