0 1 2 3 Project A -$25 $5 $10 $17 Project B -$20 $10 $9 $6 What are the projects IRRs at each of these
0 1 2 3
Project A -$25 $5 $10 $17
Project B -$20 $10 $9 $6
What are the projects IRRs at each of these WACCs? (Yes, I do need IRRs; not MIRRs. I understand that WACCs don't affect the IRRs, but I don't know the answer. Please show how to determine the answer, and the answer.)
WACC = 5%, NPVs:
Project A = 3.52 million; Project B = 2.86 million
WACC = 10%, NPVs:
Project A = .57 million; Project B = 1.04 million
WACC = 15%, NPVs:
Project A = -1.91 million; Project B = -.54 Million