0 Question 29 A project precedence relationships, activity durations, and a network diagram are shown below. Duration Activity Predecessors (days) B 5 C 4 E
0 Question 29 A project precedence relationships, activity durations, and a network diagram are shown below. Duration Activity Predecessors (days) B 5 C 4 E B.C H B,C 1 1993 9 6 3 The critical path is. OBHI OCE OBEI OCHI Previous 1 pts Tim Attem 1 H Next