1 0 . 3 . Least - laxity - first ( LLF ) is a real - time scheduling algorithm for periodic tasks. Slack time,
Leastlaxityfirst LLF is a realtime scheduling algorithm for periodic tasks. Slack time, or laxity, is the amount of time between when a task would complete if it started now and its next deadline. This is the size of the available scheduling window. Laxity can be expressed as
Laxity deadline time